The estimate for widening Columbia Avenue has risen from $38 million to $51.5 million, and the deadline moves to 2031. Aldermen approved the TDOT deal Nov. 10.

The estimated cost of widening Columbia Avenue in south Franklin has risen from $38 million to $51,494,723. The city now has until Dec. 31, 2031, to finish the job.

Both changes are in Amendment 3 to the city’s agreement with the Tennessee Department of Transportation. The Board of Mayor and Aldermen approved it Tuesday, Nov. 10.

Updated Nov. 11: Amendment 3 passed as item 23 on the consent agenda, approved in a single vote with no one voting against and no discussion, the city’s video of the meeting shows. This story was first published before the vote.

The city will not pay more under this amendment. Federal money covers 80% and the state covers the other 20%, the staff memo says. But TDOT has capped its share. Any cost above the new total would put the 20% match on the city.

The memo, the TDOT letter and the cost table are on pages 591 to 596 of the Nov. 10 meeting packet.

What the project is

The project covers Columbia Avenue, also state Route 6 and U.S. 31, from just south of Mack Hatcher Parkway to just north of Downs Boulevard.

TDOT’s description in the amendment says the road will go from three lanes to four and five lanes. It also lists:

  • sidewalks, with curb and gutter
  • bike lanes
  • transit stops and pull-outs
  • intelligent transportation system (ITS) elements

Why it costs more

City engineers drew up a new construction cost estimate this summer. It showed the project needed more money, according to the memo from Engineering Director Paul Holzen. TDOT and the Greater Nashville Regional Council, the region’s metropolitan planning organization, added funding for design, land buying and construction.

The new estimate breaks down like this:

Phase Estimated cost
Construction $28,391,000
Right-of-way (two funding lines) $16,900,000
Construction engineering and inspection $3,190,000
Design $1,694,723
Environmental study $1,000,000
TDOT engineering services $319,000
Total $51,494,723

Source: Exhibit A to Amendment 3, TDOT Agreement 140204. The right-of-way phase is listed as $12.9 million and $4 million.

That is $13.5 million, or about 36%, more than the $38 million in the 2023 version of the agreement.

Bar chart of the $51.5 million Columbia Avenue widening estimate by phase: construction $28.4 million, right-of-way $16.9 million, construction inspection $3.2 million, design $1.7 million, environmental study $1 million and TDOT engineering $0.3 million.
Where the new estimate goes, by phase. Chart by Franklin News Today from the TDOT agreement in the Nov. 10 packet.
Share this chartFacebookWhatsAppX

Eleven years and three deadlines

The board first signed the agreement with TDOT on July 14, 2015. It lets the city manage the project and draw federal money. The memo sets out how the finish date has moved:

  • Oct. 30, 2020: the original deadline.
  • Oct. 30, 2023: set in 2020, as the city was about to start buying land.
  • Oct. 31, 2026: set in November 2023. TDOT had paused land buying for an environmental review, and the city could not restart it until July 2023.
  • Dec. 31, 2031: the new date, approved Nov. 10.

The city is now in the middle of buying right-of-way and easements, the memo says. The new date “should provide enough time to finish ROW acquisition and achieve construction completion,” it says. The packet gives no construction start date.

The city’s Capital Investment Committee recommended the amendment 4-0 on Sept. 24.

What it means for you

  • If you drive Columbia Avenue: nothing changes on the road yet. Construction has not started, and the packet sets no start date.
  • If you own property along the corridor: the city is buying land and easements now. The city’s Engineering Department runs the project; our who to call at City Hall page has the numbers.
  • If you pay city taxes: this amendment adds no city cost. Future increases would, because TDOT’s cover for the local share now stops at $51,494,723.
  • Next step: the city keeps buying land and easements. The packet gives no construction start date, and we will report one when the city sets it.

For work closing lanes now, see our Franklin road construction and closures page. For the other big road debate, read about the three options for widening Franklin Road.